Home > Puma (Tdci) > Estimate on labor time |
|
|
familymad Member Since: 13 Dec 2011 Location: Bucks Posts: 3481 |
A full days labour 1951 80" S1 2.0
1995 110 300TDI 1995 90 300TDI |
||
25th Jan 2021 3:09pm |
|
Ben01 Member Since: 04 Aug 2020 Location: International Posts: 14 |
thanks, much appreciated.
|
||
25th Jan 2021 3:35pm |
|
jst Member Since: 14 Jan 2008 Location: Taunton Posts: 8021 |
thats assuming it all went to plan for a full day and depends how long a full day is.
injectors dont always come out nicely full tank , assuming comes out no rusted up tow bars etc, half a day thermostat just under an hour steering damper and steering guard and hourish fluids, filters and sensors another hr ish. Cheers James 110 2012 XS Utility 130 2011 M57 bespoke Camper 90 2010 Hardtop 90 M57 1988 Hardtop |
||
25th Jan 2021 6:08pm |
|
|
All times are GMT |
< Previous Topic | Next Topic > |
Posting Rules
|
Site Copyright © 2006-2024 Futuranet Ltd & Martin Lewis